This project involved the construction of a large scale car parking and infrastructure scheme designed to accommodate 800 vehicles.
The works included approximately 12,000m² of earthworks, comprising cut and fill operations to achieve the required formation levels, along with the installation of 1,500 linear metres of surface water drainage. A geocellular water attenuation system totalling 1,000m³ was installed to manage surface water runoff in line with sustainable drainage requirements. The scheme also included the construction and surfacing of 11,000m² of permeable car parking.
Our role
Commercial management and quantity surveying for BCE Northern on a six month NEC4 package delivered alongside live airport operations.